One Capitol Condominium
August 2008
Architectural Designs
September 2008
Project Site Soil Test
October 2008
Contract Signing and Site Office Construction
November 2008
Demolition of Existing Structure and Excavation Works
December 2008
Foundation Works and Concreting
January 2009
Excavation Works for Drainage System
February 2009
Concreting of STP Wall
Formworks at Upper Ground Floor
Rebars & Roughing in works at Upper Ground Floor (1st Half)
March 2009
Concrete Pouring of Upper Ground Floor (1st half)
Formworks, Rebars, Roughing in and Concreting for Sewage Treatment Plant (STP)
April 2009
Preparation for the concreting of upper ground level (2nd Half)
Formworks, Rebars, Roughing in and Concreting for 2nd Floor Level
May 2009
Completed rebars and utilities roughing in works at 2nd floor level.
Final cleaning of the area is on going prior to concrete pouring.
June 2009
Formworks, Rebars, Roughing in and Concreting for 3rd Floor Level.
July 2009
One Capitol as of start of July 2009.
August 2009
Structural works in full swing, ongoing at 8th floor.
September 2009
Structural works in full swing, on-going at 10th floor.
October 2009
Structural works in full swing, on-going at Penthouse Level.
|